PMP had completed 3D Model Review (60% milestone) in FEED Phase of Phu My Polypropylene Production Plant Project with FEED Contractor (Tecnimont S.P.A)
From November 06th – 11th, 2021, Phu My Plastic Production J.S.C (PMP) had cooperated the Project Management Consultant (EPC DMCC) to conduct 3D Model Review (60% milestone) at FEED Phase of Phu My Polypropylene Production Plant Project with the FEED Contractor (Tecnimont S.P.A) via video conference.
In the meeting, model of main architecture, civil, electric, control system, piping, equipment and structure had been reviewed and assessed in term of compliance with relevant regulations and standards, mandatory requirements from Licensors, to achieve:
(i) Plant layout fulfils required safety standards.
(ii) Operability, accessibility, maintenance, ability to install equipment, compliance with process requirements and construction capabilities are all met.